Transition the Main Compute PCBA from Rev B to Rev C to resolve thermal throttling caused by an obsolescence-driven voltage-regulator substitution. The new pinout requires the Compute-to-Drive Wiring Harness to move from Rev 1 to Rev 2 as well.

Closed all four mitigation outcomes: two PCBA cancellations, one accepted PCBA loss and one harness conversion. — 7/29/2026, 8:14:45 PM

Current financial position

$74,000.00

Exposure certainty

100%

Executive decision report

Preview the document, then print or export the supporting workbook.

DeltaLedger

Engineering change decision record

Confidential7/31/2026

Engineering change · Draft

ECO-1042: Main Compute PCBA Rev B → Rev C

Transition the Main Compute PCBA from Rev B to Rev C to resolve thermal throttling caused by an obsolescence-driven voltage-regulator substitution. The new pinout requires the Compute-to-Drive Wiring Harness to move from Rev 1 to Rev 2 as well.

Decision posture

Evidence supports financial review

No unresolved exposure, stale provenance, or open outcome currently prevents this record from being reviewed.

Gross exposure

$83,200.00

Mitigation benefit

$37,480.00

Remaining financial impact

$36,520.00

Evidence

100% fully verified

Prepared for financial decision reviewDeltaLedger · 01

DeltaLedger

Engineering Change Exposure & Outcome Report

Executive summary · 02

Engineering Change

ECO-1042: Main Compute PCBA Rev B → Rev C

Status

Draft

Owner

Elena Suárez (unverified)

Generated

7/31/2026, 12:31:21 AM

This engineering change is read-only. This report reflects its finalized, locked state.

EXECUTIVE SUMMARY

$74,000.00

$74,000.00 of net exposure across 4 records.

Across 4 recorded mitigation outcomes, $48,800.00 of value was avoided or preserved. $11,320.00 of mitigation costs and $25,200.00 of unavoided write-offs produce $36,520.00 of total realized loss.

Net mitigation benefit to date: $37,480.00.

Decision brief

Decision requested

Accept the financial outcome and close the change

Recommended posture

Proceed to financial review using the remaining impact and supporting evidence below.

Evidence limitation

4 of 4 exposure records are fully verified.

Gross exposure (before mitigation)

$83,200.00

Mitigation benefit to date

$37,480.00

Remaining financial impact

$36,520.00

Known, estimated, and unresolved exposure4 records total
Known$74,000.00 · 4
Estimated$0.00 · 0
Unresolved0 records

What Changed

2 parts replaced, comparing the current and proposed Bill of Materials.

Largest Financial Drivers

PartSupplier / PONet exposure
APX-8801BSunrise ElectronicsPO-3301$25,200.00
APX-8801BSunrise ElectronicsPO-3301$25,200.00
APX-8801BSunrise ElectronicsPO-3301$12,600.00
APX-4415-1Harness WorksPO-3302$11,000.00

Supplier Concentration

SupplierNet exposure
Sunrise Electronics$63,000.00
Harness Works$11,000.00

Financial Outcomes

PartEstimated (frozen)Value avoided / preservedActual lossNet benefitStatus
APX-8801B$25,200.00$25,200.00$7,560.00$17,640.00Closed
APX-8801B$25,200.00$0.00$25,200.00$0.00Closed
APX-8801B$12,600.00$12,600.00$1,260.00$11,340.00Closed
APX-4415-1$11,000.00$11,000.00$2,500.00$8,500.00Closed

Mitigation Actions

PartActionOwnerDueStatus
APX-8801Bnegotiatenr-buyer (unverified)2026-08-03Done
APX-8801Baccept lossnr-buyer (unverified)2026-08-03Done
APX-8801Bcancelnr-buyer (unverified)2026-08-03Done
APX-4415-1redirectnr-buyer (unverified)2026-08-03Done

Key Decision History

The most consequential recorded activity for this engineering change. Repeated form submissions and correction steps are condensed here; the complete, append-only record remains available in Audit Trail.

WhenActorAction
7/29/2026, 8:14:45 PMJames WhitfieldClosed all four mitigation outcomes: two PCBA cancellations, one accepted PCBA loss and one harness conversion.
7/29/2026, 8:14:40 PMJames WhitfieldApproved alternate demand for 50 Rev-B PCBAs as field-service spares and 100 Rev-1 harnesses for the installed service fleet.
7/29/2026, 5:12:05 PMElena SuárezCalculated Week-0 baseline exposure against the imported open POs.
7/29/2026, 5:12:03 PMElena SuárezGenerated and approved part-number mappings for the PCBA and harness.
7/29/2026, 5:12:03 PMElena SuárezRecorded supplier commitment terms for Sunrise Electronics and Harness Works.
7/29/2026, 5:12:02 PMTasha ReyesImported open PO export (4 lines, 2 supplier(s)): PO-3301 (Sunrise Electronics, PCBA, 3 batches) and PO-3302 (Harness Works, harness).
7/29/2026, 5:12:02 PMElena SuárezImported current and proposed BOM; explicitly paired the PCBA and harness replacements.
7/29/2026, 5:12:00 PMElena SuárezCreated engineering change "ECO-1042: Main Compute PCBA Rev B → Rev C" for Nova Robotics, Inc. (fictional demonstration company).

Provenance & Calculation Method

Each exposure record is classified Known, Estimated, or Unresolved based on whether its part mapping and PO currency data are fully confirmed. Unresolved records carry no dollar figure by design -- they are counted, never estimated at zero -- so they can never quietly understate real exposure. All calculations are deterministic: identical inputs always produce identical results, and every superseded calculation remains in this system’s history rather than being overwritten.

Appendix: BOM & Purchase Order Summary

replaced

2

Generated by DeltaLedger on 7/31/2026 · Deterministic calculations from persisted exposure and outcome records · Confidential