ECO-1042: Main Compute PCBA Rev B → Rev C

Read-only

Transition the Main Compute PCBA from Rev B to Rev C to resolve thermal throttling caused by an obsolescence-driven voltage-regulator substitution. The new pinout requires the Compute-to-Drive Wiring Harness to move from Rev 1 to Rev 2 as well.

Closed all four mitigation outcomes: two PCBA cancellations, one accepted PCBA loss and one harness conversion. — 7/29/2026, 8:14:45 PM

Current financial position

$74,000.00

Exposure certainty

100%

MAPPING

All mappings approved and current

This screen confirms which part number your ERP actually recognizes for each engineering-changed part -- no dollar figure downstream in Exposure is trusted until that's settled. Only Part Data Owner or Admin may approve, reject, revise, or revoke a mapping.

Why this matters

Connect engineering part numbers to the identifiers used in purchasing so commitments are attributed to the correct parts.

DeltaLedger uses

The affected BOM parts, imported PO part numbers, and deterministic match suggestions.

You are done when

Each affected part is approved or intentionally left unresolved with its financial limitation clearly disclosed.

This engineering change is read-only. Actions below are disabled for this scenario.

Every eligible part has an approved mapping. Exposure can now be calculated on the full, resolved set.

Continue to Exposure →
APX-8801B100% matchexact
approved

Exact string match against "APX-8801B" in the open PO import.

100% match confidence
APX-4415-1100% matchexact
approved

Exact string match against "APX-4415-1" in the open PO import.

100% match confidence