ECO-1042: Main Compute PCBA Rev B → Rev C

Read-only

Transition the Main Compute PCBA from Rev B to Rev C to resolve thermal throttling caused by an obsolescence-driven voltage-regulator substitution. The new pinout requires the Compute-to-Drive Wiring Harness to move from Rev 1 to Rev 2 as well.

Closed all four mitigation outcomes: two PCBA cancellations, one accepted PCBA loss and one harness conversion. — 7/29/2026, 8:14:45 PM

Current financial position

$74,000.00

Exposure certainty

100%

The scenario

Nova Robotics is transitioning its Main Compute PCBA from Rev B to Rev C to resolve thermal throttling. This workspace reconciles the resulting open commitments with verified supplier terms, reviewed field-service demand and mitigation evidence through one fictional, read-only engineering change.

Ready for financial review

The current evidence supports a decision.

Every required workflow check has passed against the latest recorded data.

Current financial position

$74,000.00

Known

$74,000.00

Estimated

$0.00

Unresolved

0 records

Next best action

No blocking action

Required workflow stages are complete. Review the consolidated financial result and evidence record.

Open executive report

Source data

BOM and commitments ready

BOM loaded · PO data loaded

Part identity

Mappings reviewed

No pending mapping reviews

Response & outcome

Outcomes complete

No unresolved outcomes

Most recent activity

Closed all four mitigation outcomes: two PCBA cancellations, one accepted PCBA loss and one harness conversion. — 7/29/2026, 8:14:45 PM